| change out of 110 ton chiller and 70 ton ahu | 2012-08-09 | BUILDING | - | - |
| No Description | 2012-03-14 | BUILDING | - | - |
| change out 2 ton | 2012-03-14 | Hvac / Mechanical Velocity Hall Permit | - | - |
| No Description | 2012-03-09 | BUILDING | - | - |
| changeout 2 ton unit | 2012-03-02 | Hvac / Mechanical Velocity Hall Permit | - | - |
| No Description | 2011-12-09 | BUILDING | - | - |
| changeout 2 ton and 2.5 ton units | 2011-12-06 | BUILDING | - | - |
| changeout 2.5 ton split system | 2011-11-16 | BUILDING | - | - |
| *install manual barometric damper in return air for small... | 2011-10-13 | BUILDING | - | - |
| Change out 2 ton- 3 offices 2 ton SSHP in lunch room | 2011-09-29 | BUILDING | - | - |
| replace 3 ton ac unit | 2011-09-19 | BUILDING | - | - |
| Replace 2 HVAC units- 5 ton and 7.5 ton | 2011-08-05 | BUILDING | - | - |
| 3 ton changeout | 2011-04-15 | BUILDING | - | - |
| No Description | 2011-02-24 | BUILDING | - | - |
| No Description | 2011-02-14 | BUILDING | - | - |
| 4 ton ahu changeout | 2011-02-11 | BUILDING | - | - |
| Changeout 2 Ton Unit | 2010-11-29 | Hvac / Mechanical Velocity Hall Permit | - | - |
| Changeout 5 ton system | 2010-09-22 | BUILDING | - | - |
| system changeout 2 ton | 2010-09-17 | BUILDING | - | - |
| changeout of 5 ton unit | 2010-08-06 | BUILDING | - | - |
| Install 3x 2 ton bard unit | 2010-06-02 | BUILDING | - | - |
| No Description | 2010-04-02 | BUILDING | - | - |
| heat pump changeout | 2010-03-09 | BUILDING | - | - |
| EXISTING TAP | 2010-01-13 | BUILDING | - | - |
| Change out 4 Ton HVAC system | 2009-12-18 | BUILDING | - | - |
| apt 149 complete 2 ton system change out. apt 195 Condens... | 2009-04-20 | BUILDING | - | - |
| changeout of owner provided 2 ton split system straight c... | 2009-02-04 | BUILDING | - | - |
| existing tap | 2009-01-30 | BUILDING | - | - |
| Installation of Owner Provided New 70 Ton Trane Screw Chi... | 2009-01-16 | BUILDING | - | - |
| hvac unit changeout for apt 308 | 2008-11-26 | BUILDING | - | - |
| condenser changeout apt 185 | 2008-10-31 | BUILDING | - | - |
| changeouts | 2008-10-17 | BUILDING | - | - |
| conedensor changeout in apt 508 and 908 | 2008-10-16 | BUILDING | - | - |
| Install minisplit owner provided | 2008-10-16 | BUILDING | - | - |
| HVAC changeout at Duval on Green Apt 106 | 2008-09-30 | BUILDING | - | - |
| changeout 705 | 2008-09-24 | BUILDING | - | - |
| changeout in apt 305 and 1104 | 2008-09-16 | BUILDING | - | - |
| changeout condensors in apt 108,712, 701 | 2008-08-05 | BUILDING | - | - |
| changeout condenser for a two ton and 5 ton units | 2008-07-21 | BUILDING | - | - |
| Changeout for apt 106 | 2008-07-14 | BUILDING | - | - |
| 2 ton unit changeout of AHU/HP system #2 | 2008-07-08 | BUILDING | - | - |
| apt c replace 2 ton condensing unit | 2008-06-30 | BUILDING | - | - |
| changeout 2 ton condenser for apt 84 and 135 Duval on the... | 2008-06-20 | BUILDING | - | - |
| 2 ton condenser changeout | 2008-06-20 | BUILDING | - | - |
| 2 ton condensor changeout for apt 1303 and 1304 | 2008-06-10 | BUILDING | - | - |
| changeout 4 ton heat pump | 2008-06-06 | BUILDING | - | - |
| changeout air handler | 2008-01-08 | BUILDING | - | - |
| A/C unit changeout | 2007-07-25 | Hvac / Mechanical Velocity Hall Permit | - | - |
| replacement of 10 ton air handler | 2007-07-16 | BUILDING | - | - |
| Boiler stack and exhaust duct | 2007-07-02 | Hvac / Mechanical Velocity Hall Permit | - | - |